HXD1 locomotive project

  • HXD1 locomotive project
HXD1 locomotive project
  • Product Presentation

1544409200901025092.png

         

        In November 2003, the Ministry of Railways of China and the former China South Locomotive, CNR Group and its key enterprises jointly formulated the Outline for Accelerating the Modernization of Railway Locomotive and Vehicle Equipment, and selected six locomotive manufacturing enterprises as the introduction of advanced technology and independent innovation. The subject. At the beginning of December 2004, according to the state arrangement, Siemens and former CSR Zhuzhou Electric Locomotive Works Co., Ltd. obtained an order for 180 double-axle eight-axle heavy-duty freight AC drive electric locomotives from the Ministry of Railways of China, with a total value of about 7.34 billion. Yuan Renminbi, of which Siemens' share is about 350 million euros, while Zhuzhou Electric Locomotive Works has a share of 52.6%, about 3.86 billion yuan.

        The HXD1 project was designed by the Siemens Transportation Group headquarters in Germany, and the Zhuzhou Electric Locomotive Works was produced in Zhuzhou, Hunan. The locomotive consists of two identical four-axle locomotives. It uses AC-DC-AC drive, water-cooled IGBT traction inverter, variable frequency asynchronous traction motor, "SIBAS 32" microcomputer control system and train communication network. The rated power is 9600. Kilowatts, with a maximum operating speed of 120 km / h, and equipped with "Locotrol" remote reconnection control system, suitable for multi-machine distributed heavy-duty traction. Up to the current total production and production: 300 units, all running on the Daqin Railway.


Development process

 China and the German government signed a project procurement memorandum on December 6, 2004

Project launch in January 2005

 In December 2005, Siemens, the Zhuji Federation and the Ministry of Railways of China confirmed the technical plan.

In February 2006, the technical design proposal passed the technical review of the Ministry of Railways.

On November 8, 2006, the first locomotive was completed and offline.

 Type test and comprehensive performance test were completed from February to April 2007

In May 2007, the pilot application of the Daqin Railway was put into use.

 At the end of July 2007, it began to take the traction task of the 20,000-ton combined train on the Daqin line.


Key technical parameters

Current system: single phase AC 25 kV, 50 Hz

Locomotive traction / electric brake wheel power: 9600kW

HXD1-0001 axis: 2 (B0-B0)

Gauge: 1435mm (quasi)

Locomotive weight: 2×92t/2×100t

Axle weight: 23t / 25t

Center distance between front and rear hooks of locomotive: 35222 mm

Single locomotive bogie center distance: 9000 mm

Bogie fixed wheelbase: 2800 mm

Wheel diameter: 1250 mm (new wheel)

Maximum speed: 120 km / h

Electric braking force: 461kN


Our product advantages:

Operating temperature range -40 to +70 °C

According to the standard: IEC60571, IEC60077 (GB21413), EN50155, etc.

Anti-vibration and shock resistance

Meets the vibration and shock resistance requirements of EN50155, IEC61373;

Cage spring clamping technology ensures that the product is reliably connected under vibration conditions.

Low smoke, halogen free, flame retardant

Meets EN45545 (HL1 ~ HL3) fire protection standards

Wide voltage range:

Control voltage range from 0.7 to 1.25Us, integrated surge suppressor

 According to the standard: IEC60571, IEC60077 (GB21413), EN50155, etc.


Application case: HXD1 locomotive project

1544409569892052585.png