Changsha office 0731-88922097
Zhuzhou office 0731-22867780
DETAILSPAGEProduct CenterTechnical SolutionProject Case |
Particulars
The Guangzhou Rail Transit Line 3 vehicle project is a B-type vehicle project independently developed and manufactured by CRRC CSR. The entire project is 26 columns, 6 sections (4 sections of trains, 2 sections of trailers), a total of 156 vehicles. Adopt DC1500V overhead rigid contact net to receive flow; B-type aluminum alloy body; bogie is independently developed by the company, namely ZMA120 high-speed B-type bogie. The vehicle has a top speed of 120km/h and a construction speed of 135km/h. At present, the CRRC car in the Guangzhou area has successively obtained the 128th, 28th, Guangfo, 7th, 9th, 14th, 18th, and 21st lines in Guangzhou. Train orders for subway projects. Development process Signed a project contract in November 2003 Project launch in March 2004 Approved by the electric drive system program in June 2004 Approved by the overall technical program in September 2004 The first train was dropped in April 2005 The first section of the operation was opened on December 26, 2005 (Guangzhou East Railway Station to Kecun Station)
The train formation map is as follows Our product advantages: Operating temperature range -40 to +70 °C According to the standard: IEC60571, IEC60077 (GB21413), EN50155, etc. Anti-vibration and shock resistance Meets the vibration and shock resistance requirements of EN50155, IEC61373; Cage spring clamping technology ensures that the product is reliably connected under vibration conditions. Low smoke, halogen free, flame retardant Meets EN45545 (HL1 ~ HL3) fire protection standards Wide voltage range: Control voltage range from 0.7 to 1.25Us, integrated surge suppressor According to the standard: IEC60571, IEC60077 (GB21413), EN50155, etc. Previous: Malaysia SCS Train Project
Next: No information found
|